Back
to top of page
|
Joint
Coastal Permit Fees
|
|
Chapter
62B-41.0085(3), F.A.C. (Also includes fees from Chapter 62B-4,
F.A.C.)
|
|
1)
Applications for construction and major
modifications to existing coastal structures, any
part of which are sited seaward of mean
high-water on sovereignty submerged lands, shall
be assessed a fee in accordance with the
following schedule:
|
|
a)
Rigid coastal structures:
|
|
1)
Up to 100 feet in length.
|
$2,000 |
2)
For each additional 50 feet
of length or portion thereof.
|
$500 |
b)
Beach restoration
|
|
1)
For first 50,000 cubic yards
of fill.
|
$2,000 |
2)
For each additional 50,000
cubic yards of fill, or portion thereof.
Back
to top of page
|
$500 |
c)
Construction and maintenance dredging of
inlets:
|
|
1)
For the first 10,000 cubic
yards of dredged material
|
$2,000 |
2)
For each additional 10,000
cubic yards of dredged material or portion
thereof if such material is placed in an
upland or offshore disposal site.
|
$250 |
3)
For each additional 50,000
cubic yards of fill or portion thereof if
such material is placed on the beach or
approved nearshore area.
|
$500 |
d)
Inlet-related structures, major reconstruction
and other major structures and activities: per
structure.
|
$1,000 |
e)
Minor structures and activities, minor
reconstruction of existing structures, amended
applications, major modifications to existing
permits and administrative approval of each
subsequent nourishment or maintenance dredging
operation.
|
$500 |
f)
Requests for renewal reviews for long
term inlet maintenance dredging permits.
|
$750 |
g)
Requests for time extensions or transfer
of existing permits.
Back
to top of page
|
$100 |
| 2)
Permit fees for each individual structure,
except minor structures, shall be added together
for each application. |
|
| 3)
The cost for special public notice
incident to issuing permits under this Chapter
shall be borne by the applicant. If the
Department of Environmental Protection incurs any
expense, notice to proceed shall not be issued
until such costs are reimbursed. |
|
| 4)
For projects which are cost-shared under
Chapter 62B-36, F.A.C. with the state government,
the local government may request waiver of the
that portion of the fee above the local
government pro rata share. In no case will the
local pro rata share be less than $2,000. |
|
| 5)
Experimental projects permitted under rule
62B-41.0075 shall be assessed the larger of a fee
of $5000, or the permit fee specified in the
appropriate fee schedule above, except the
maximum fee shall not exceed $20,000. |
|
| 6)
The Department is authorized to waive the
permit application fees for removal, without
replacement, of existing derelict coastal
structures if a determination is made that they
serve no public purpose, endanger human life,
health or welfare, or are unnecessary or
undesirable. |
|
Back
to top of page
Environmental
Resource Permit Fees - Chapter 62-4.050(4)(g), F.A.C.
|
Individual
and Conceptual Approval Permits
|
|
(those
systems that involve > 1 acre of
construction or alteration in, on or over
wetlands or other surface waters, involve >
10 new boat slips, are capable of impounding >
120 acre feet, serve a total land area >
100 acres, or provide for the placement of >
12 acres of impervious surface.) |
| 1) For
a system that involves <1 acre of construction
alteration in, on or over wetlands or other
surface waters and involves < 10 new boat
slips but reaches any of the following three
thresholds: |
|
a)
is capable of impounding > 120 acre
feet
b) serves a total land
area > 100 acres; or
c) provides for the
placement of > 12 acres of impervious
surface.
|
$2,500 |
| 2) For
a system involving the following total acreage of
construction or alteration in, on or over
wetlands or other surface waters: |
|
a)
>
100 acres
|
$10,000 |
b)
< 100 acres and >
50 acres
|
$8,000 |
c)
< 50 acres and > 10 acres
|
$6,500 |
d)
< 10 acres and > 5 acres
|
$5,500 |
e)
< 5 acres and > 2 acres
|
$4,000 |
f)
< 2 acres and > 1 acre
Back
to top of page
|
$3,000 |
|
Standard
General Permits |
|
(those
systems below the thresholds listed above) |
| 1)
For a system serving a project with a
total land area < 100 acres and > 40
acres, with the following additional activities: |
|
a)
Either the construction of 1- 9 new boat
slips or the construction or alteration (other
than new boat slips) in, on or over a total
area of wetlands or other surface waters < 1
acre and > 0 acres.
|
$1,000 |
b)
No construction or alteration in, on or
over wetlands or other surface waters.
|
$700 |
| 2)
For a system serving a project with a
total land area < 40 acres and > 1 acre
involving construction or alteration (other than
new boat slips) in, on or over a total area of
wetlands or other surface waters < 1 acre and
> 0 acres. |
$600 |
| 3)
For a system serving a project with a
total land area < 1 acre, involving
construction or alteration (other than new boat
slips) in, on or over a total area of wetlands or
other surface waters < 1 acre and > 0
acres. |
$500 |
| 4)
Environmental Resource Permit for a system
serving a project with a total land area < 40
acres and involving no construction or alteration
in, on or over wetlands or other surface waters.
Back
to top of page
|
$300 |
|
Noticed
General Permit |
|
Noticed
General Permit |
$100 |
|
Modifications |
| 1)
For major modifications of Individual and
Conceptual Approval Permits (no increase in
project area.) |
$700 |
| 2)
For major modifications of Individual and
Conceptual Approval Permits (with an increase in
project area). |
$2,000 |
| 3)
For major modifications of Standard
General Permits. |
50%
of original application fee |
| 4)
For permit extensions. |
$50 |
|
Variances |
|
Variances |
$500 |
Back
to top of page
|
Wetland
Resource Permit (Dredge and Fill Permit) Fees |
|
Chapter
62-4.050(4)(d), F.A.C. |
|
These
permit fees pertain to projects that have been
grandfathered according to Sections
373.414(11)(1994 Supp.), (12)(a)(1994 Supp.),
(13), (14), (15) or (16), F.S. and projects, or
portions thereof, located in the Northwest
Florida Water Management District. |
| 1)
Dredge and fill construction projects up
to and including 5 years: |
|
a)
Standard form projects including dredge
and fill activities that affect 10 or more
acres of jurisdictional area
pursuant to Rule 62-312.070(2), F.A.C.
|
$4,000 |
b)
Short form construction projects
involving dredging and filling activities that
affect 9.99 acres or less of jurisdictional
area, pursuant to Rule 62-312.070 (2), F.A.C.
|
$500 |
| 2)
Dredge and fill construction permits in
excess of 5 years: |
|
a)
Short form permits from 6 years up to
and including 10 years.
|
$3,000 |
b)
Standard form permits over 5 years
|
$1,000
per year total |
c)
6 to 10 year permits for beach
restoration projects approved pursuant to
Chapter 161, F.S., and to maintenance dredge
navigation channels, port harbors, turning
basins and harbor berths located within
deepwater ports, pursuant to Section 403.816,
Florida Statutes.
|
$5,000 |
|
Modifications |
Modifications
|
$250 |
|
Variances |
Variances
|
$500 |
Back
to top of page
|
Sovereignty
Submerged Lands Authorization Fee
|
|
Chapter
18-21.008, .009, or .010, F.A.C. |
| a)
Fee for processing an easement or lease
application
|
$200 |
More
Information
Joint
Coastal Permit fees are the sum of the fees
required by 62-4.050(4)(d) or (g), 62B-41.0085(3), and
18-21.008, .009, or .010, F.A.C. Environmental
Resource Permit fees are the sum of the fees
required by 62-4.050(4)(g) and 18-21.008, .009, or .010.
Wetland Resource Permit fees are
the sum of the fees required by 62-4.050(4)(d) and
18-21.008, .009, or .010. For more information
regarding these fees, please contact the
Environmental
Permitting staff.
Back