Florida Department of Environmental Protection Florida Department of Environmental Protection
More Protection, Less Process
* DEP Home * About DEP * Programs * Contact * Site Map * Search
MyFlorida.com  
Conditions of Certification Highlights

Under the various Siting Acts, the approval is known as "Certification", and the licensing provisos or restrictions are known as Conditions of Certification.

   Eventually all of the Conditions will be converted to .pdf format and require the free Adobe Acrobat Reader Software (see left side bar) to open and save. The listing is in the order of the Siting Case Number (see second column). 

Note: There may be errors derived from translation into electronic mode. For an official version of the Conditions, you MUST consult with the Siting Coordination Office.

The Department's Office of General Counsel is responsible for the Final Orders


 


Power Plant Siting
Conditions of Certification

 

 

Case Name Siting Case No. & Module No. Comments
FP&L's Putnam Plant PA74-01

8011

Modified 12/01/05
FP&L's St. Lucie #2 PA74-02

8012

Modified 04/14/06
Tallahassee's Hopkins PA74-03

 8013

Modified 11/13/06
Gainesville's Deerhaven PA74-04

8014

Modified 08/17/07
Lake Worth Unit S-5 PA74-05

8015

Modified 03/29/96
Lakeland/OUC's
McIntosh #3 & #5

PA74-06

8016

Modified 7/01/08
Gulf Power's Caryville PA75-07

8017

Certified 05/07/76; never constructed
Dade. Co. Resource Recovery Facility PA77-08

8018

Modified 02/07/06
FPC's Crystal River 4 & 5 PA77-09

8019

Modified 08/07/08
Seminole's 1 & 2 (Palatka) PA78-10

8020

Modified 09/06/06
Pinellas Co. Resource Recovery Unit PA78-11 + PA83-18

8021

Modified 02/15/07
TECo's Big Bend 4 PA79-12

8022

Modified 02/28/07
JEA's St. John's River Power Park PA81-13

8023

Modified 03/08/07
OUC's Stanton Units 1 & 2 and Combined Cycle Unit A and Unit B

PA81-14

8024

Modified 07/24/08
Fla. Crushed Stone PA82-17

8025

Modified 12/04/07
Hillsborough Co. Resource Recovery Facility PA83-19

8026

Modified 03/07/07
Palm Beach Co. Resource Recovery Facility PA84-20

8027

Modified 04/08/08
South Broward Resource Recovery Facility PA85-21

8028

Modified 08/11/05
North Broward Resource Recovery Facility PA86-22

8029

Modified 02/01/05
Pasco Co. Resource Recovery Facility PA87-23

8030

Modified 05/09/07
Cedar Bay PA88-24

8031

Modified 08/17/07
TECo PA89-25

8035

Modified 08/09/06
Modified 07/25/06
FP&L's Lauderdale PA89-26

8036

Modified 07/24/06
FP&L's Martin PA89-27

8037

Modified 07/09/07
Lee County Waste-to-Energy Facility PA90-30

8040

Modified 05/07/07
Indiantown PA90-31

8041

Modified 03/07/07
TECo Polk

PA92-32

8042

Modified 02/29/08
FPC's Hines Units 1 - 4 PA92-33

8043

Modified on 03/29/07
Tallahassee's Purdom Unit 8 PA97-36

8046

Modified 07/29/05
FPC's Tiger Bay PA97-37

8047

Modified 11/29/06
KUA’s Cane Island Unit 3 PA98-38

8048

Modified 07/12/06
Gulf Power's Lansing Smith Unit 3 PA99-40

8050

Modified 06/17/05
Calpine's Osprey PA00-41

8051

Modified 01/09/06
JEA's Brandy Branch PA00-43

8053

Modified 07/18/07
FPL's Manatee

PA02-44

8045

Modified on 03/19/07
FPL Turkey Point

PA03-45

8055

Modified on 04/24/07
New Hope Okeelanta

PA04-46

8054

Certified on 05/26/05
Treasure Coast Energy Center

PA05-48

8057

Modified on 11/29/06
West County Energy Center

 

PA05-47

8056

Modified on 3/27/07

Power Plant Projects Withdrawn, Denied, or Application Not Filed

         Project                                                 Case Number                             Comment

FPC's Taylor PA81-15 Notice of Intent filed, but not application
FPC's Port St. Joe PA81-16 Notice of Intent filed, but not application
CMI's Pine Level PA90-28 application withdrawn
Bradley Junction PA90-29 application withdrawn
FP&L's Cypress PA92-34 application withdrawn
FP&L's Manatee Conversion PA94-35 certification denied
Duke/New Smyrna Beach PA98-39 application withdrawn

 


 

Transmission Line Cases

 

Case Name

Case Number

Comments

Tallahassee's Hopkins-Bainbridge

TA81-01

Certified 08/04/81

FPC's Central Fla.-Kathleen

TA81-02

Last modified 11/03/04

FP&L's Duval-Poinsett

TA81-03

Certified 10/18/82

FP&L's Midway-Jensen-Crane

TA81-04

Certified 01/17/84

FP&L's Crane-Bridge- Plumosus

TA88-06

 Modified 12/12/06

FP&L's Levee-Midway

TA89-07

  Certified 04/20/90

Seminole/JEA's Seminole- Keystone-Firestone

TA90-08

  Certified  06/12/91

FPC's Debary-Winter Springs

TA92-09

  Certified 05/11/93

FPL's Collier-Orange River

TA03-12

  Modified 01/05/05

FPL's St. John Pellicer-Pringle

TA05-13

Certified 04/27/06

TECO Willow Oak-Wheeler Davis

TA07-15

  Certified 08/07/08

Transmission Line Siting Projects Withdrawn or On Hold

FPC's Lake Tarpon-Kathleen

TA85-05

Certification Relinquished 03/05/96

FP&L's Orange River-Barcola

TA92-10

Application not filed; project on hold

FPC's Florida-Georgia

TA93-11

Application not filed; project on hold

 

 

 

 

NEW

Last updated: August 13, 2008

  2600 Blair Stone Rd M.S. 48   Tallahassee, Florida 32399   850-245-8002 (phone) /  850-245-8003 (fax)
 