|
TABLE
OF CONTENTS
Introduction
Preparation of the Application
Data Requirements
State Action on Submitted Applications
Applicant Information
1. Project Overview
1.1 Project Introduction
1.2 Corridor Location and
Layout
1.3 Transmission Line and Road
Design Characteristics
1.4 Proposed Intermediate
Substations
1.5 Cost Projections
2. Background Features of the Proposed
Corridor
2.1 Corridor Selection
2.2 Socio-Political
Environment of the Corridor Area
2.2.1 Governmental
Jurisdictions
2.2.2 Zoning
and Land Use Plans
2.2.3 Easements,
Title, Agency Works
2.2.4 Archeological
and Historic Sites
2.3 Bio-Physical Environment
of the Corridor Area
2.3.1 Land
Use/Vegetation
2.3.2 Affected
Waters and Wetlands
2.3.3 Ecology
2.3.4 Other
Environmental Features
3. Effects of Right-of-Way Preparation and
Transmission Line Construction
3.1 Construction Techniques
3.2 Impact on Waterbodies and
Uses
3.2.1 Preliminary
Assessment Data
3.2.2 Actual
Site Data
3.3 Solid Wastes
3.4 Changes to Vegetation,
Wildlife and Aquatic Life
3.5 Impact on Human
Populations
3.6 Impact on Archaeological
and Historic Sites
4. Effects of Transmission Line
Right-of-Way Maintenance and Post-Construction Impacts
4.1 Maintenance Techniques
4.2 Multiple Uses
4.3 Changes in Species
Population
4.4 Effects of Public Access
4.5 Electric and Magnetic
Field Effects
5. Variances, Exceptions, Exemptions
INTRODUCTION
This application form has been prepared by the
Department of Environmental Regulation to guide
utilities in the preparation of an application for
transmission line corridor certification, and to aid
affected state agencies, local governments, and
interested persons in the review of an application.
However, it should not be considered an application to
DER alone, as the data supplied must address the
licensing information requirements of all state,
regional, and local agencies with jurisdiction over the
proposed activities. This form, referenced in Chapter
17-17, Part II, Florida Administrative Code, outlines
the prescribed format for the submission of complete
and sufficient applications. Transmission lines which
are covered under the Florida Electrical Power Plant
Siting Act, transmission lines which are less than 230
kv or do not cross a county line, or other transmission
lines exempted by the Transmission Line Siting Act are
not covered by this procedure.
Prior to issuance of a corridor certification,
the Department of Environmental Regulation, Game &
Fresh Water Fish Commission, Department of Community
Affairs, Public Service Commission, Department of
Natural Resources, and local governments, water
management districts, and regional planning councils
through the jurisdiction of which the corridor would
pass are required to assess the potential effects by
the proposed transmission lines in order to ensure
through available and reasonable methods that the
location of transmission line corridors and
construction and maintenance of transmission lines will
produce minimal adverse effects on the environment and
public health, safety, and welfare (Transmission Line
Siting Act, Chapter 403, Part II, Florida Statutes).
Terms used in this form shall have the same
meaning set forth in Section 403.522, F.S., and Section
17-17.52, Florida Administrative Code.
PREPARATION
OF THE APPLICATION
The format of the application is intended to
minimize the efforts of the applicant, the reviewing
agencies, and others in the preparation and assessment
of the application. Prior to the filing of a
certification application, an applicant may request a
meeting with the department and all statutory parties
to review the applicant's plans and information
requirements for the certification pursuant to FAC Rule
17-17.54. The plans to be reviewed should be made
available to each of the statutory parties for review
at least 30 days before the meeting, but no less than
14 days. The department will give notice of such
meetings in the Florida Administrative Weekly as
provided in Chapter 17-1, Florida Administrative Code,
to all statutory parties, and to any persons who have
indicated in writing to the department an intention to
become a party. At least 7 days prior to the meeting,
the department will notify the applicant of all parties
to whom the department sent actual notice of the
meeting. The purpose of the meeting will be to
determine the scope, quantity, and specificity of
information to be included in the application and to
reach agreement in writing on the methods to be used in
providing such information, and the nature of
supporting documents to be included in the application.
As dictated by the nature of the applicant's proposed
transmission line(s) and corridor(s), the department,
the applicant, and other agencies required to provide a
report under the Transmission Line Siting Act may
agree, in writing, that certain portions of the
information requirements shall not be applicable to the
applicant's submittal.
It is not contemplated that all sections of this
form need to be extensively discussed in all
applications. In some instances "not
applicable" or a general statement may be
sufficient.
DATA
REQUIREMENTS
Information obtained from state, federal, local
and regional governmental agencies, educational
institutions and qualified consultants may be used when
completing the application. All published documents
used as supporting data must be referenced and if not
publicly available, shall be made available to the
statutory agencies upon request. If the applicant or
his consultant gathers additional information regarding
air and water quality, noise conditions, solid wastes
or other environmental impacts, the methods shall be
those duly adopted, published or otherwise approved by
the Department of Environmental Regulation.
Commonly available information and materials may
be incorporated in the application by reference. The
incorporated material shall be cited in the application
and its content described briefly. The applicant shall
indicate where the referenced material may be obtained.
Upon a written request by any party, the applicant
shall make available for copying materials unavailable
through other public sources and these shall be
provided in accordance with FAC Rule 17-17.65(3).
Concise descriptive or narrative text, as well
as, tables, maps, charts, graphs, etc., should be used
where possible. Data may be summarized by giving
maximums, minimums, and averages. However, each subject
should be documented and treated in sufficient depth to
permit the reviewer to readily evaluate the extent of
the environmental impact. Graphic displays, conceptual
drawings, and photographs should be used where they
contribute to the clarity and brevity of the
application. Cross-referencing is strongly recommended.
Maps provided for this section should be no
greater than 11 x 17 inches in size (preferably 8
1/2" by 11" for ease of distribution) and
should use graphic patterns rather than colors to
indicate various features (maps are frequently
reproduced for interested persons or conditions of
certification, and the colors do not reproduce). Unless
otherwise specified in the application, all maps shall
use a scale of at least 1:24,000, and requested data
shall be provided for the area within the corridor and
the area extending one-quarter mile on either side of
the corridor. The Department may require that more
detailed scale maps be provided to depict route areas
within 500 feet of developed residential or commercial
areas or those special protection areas itemized in
2.2.1. The applicant shall verify that data contained
in any maps and aerial photographs (e.g., land
use/vegetation overlays on to U.S.G.S. base maps) are
representative of the route area and current within 12
months of filing. Aerial photographs must be legible
reproductions.
If the applicant proposes more than one
transmission line corridor or certification, the
applicant shall provide the information requested in
this application for each proposed corridor. The
applicant may combine the information for the corridors
in the same tables, maps, charts, graphs, or other
materials, as well as in the written text, but shall
clearly identify which is the primary corridor proposed
versus secondary corridors.
STATE
ACTION ON SUBMITTED APPLICATIONS
The
State's procedures for submitted applications are
outlined in Sections 403.52-539, Florida Statutes, and
also the Department of Environmental Regulation's
companion rule Chapter 17-17, Part II, Florida
Administrative Code, and the Public Service
Commission's companion rules 25-22.75 and 25-22.76,
Florida Administrative Code.
Certification in itself does not convey title or
grant easements for any property, state-owned or
otherwise. Therefore, where the applicant desires to
use or cross state-owned lands, the appropriate
government agencies should be contacted regarding the
use of public properties.
APPLICANT
INFORMATION
Please
supply the following information:
Applicant's
Official Name
_______________________________________________________
Address
________________________________________________
Business
Entity (corporation, partnership, co-operative, names,
owners, etc.)
_______________________________________________________
Name
and Title of Chief Executive Officer
________________________________________________________
Name,
Address, and Phone Number of Official Representative
responsible for obtaining certification:
_______________________________________________________
Corridor
Location (counties crossed)
________________________________________________________
Incorporated
Cities within the corridor (names)
________________________________________________________
Termination
Points
_________________________________________________________
Intermediate
Substations
_________________________________________________________
Voltage
___________________________________________________
Line
Type (AC or DC)
_________________________________________________________
Length
of line and number of circuits
_________________________________________________________
Remarks
(if any):
_________________________________________________________
CHAPTER
1
PROJECT
OVERVIEW
The transmission line corridor and transmission
lines to be built within a right-of-way in the corridor
are to be discussed in this chapter. The best estimates
of the characteristics of the proposed corridor should
be described in as much detail as possible.
1.1
Project Introduction
Explain the proposed transmission configuration,
summarizing similar information provided to the Public
Service Commission for the Need Determination
proceedings. If available, provide the Order entered by
the PSC on the need for the transmission line. Clearly
indicate the termination points for the transmission
line (substations, power plants, transmission networks
or rights-of-way) and differentiate between those
proposed versus existing.
Discuss the corridor width requested to be
certified, the right-of-way width to be located within
the corridor, and the number and size of transmission
lines proposed to be located on that right-of-way.
1.2
Corridor Location and Layout
Depict the proposed corridor(s) on route
identification maps at a scale of at least 1:126,720
which generally indicates the full length of the
corridor(s) relative to major geographic features.
These maps should also depict any other 115 KV or
larger transmission lines already in place within 5
miles of the centerline of any corridor proposed for
certification.
1.3
Transmission Line and Road Design Characteristics
Describe the proposed transmission line design
and include basic design parameters such as voltage,
capacity under normal and emergency conditions, typical
conductor types and configurations, approximate spans,
and minimum conductor clearances. Illustrate the type
of transmission structures proposed, and provide a
profile of the structures and conductors.
Estimate the number, length, width, and general
location of new access and service roads or bridges
reasonably expected to be required. Generally describe
the type of access roads that will be required.
1.4
Proposed Intermediate Substations
If proposed intermediate substations are planned,
discuss the rationale for choosing the general location
of the substations, including pertinent remarks, if
any, made by the PSC in their determination of need.
1.5
Cost Projections
Provide an estimated cost range each corridor
proposed, broken down into per-mile estimated cost
range and cost range for: land acquisition,
right-of-way preparation, road construction and fill
costs; erected tower costs including tangent and angle
structures, and conductor stringing.
CHAPTER
2
BACKGROUND
FEATURES OF THE PROPOSED CORRIDOR
2.1
Corridor Selection
Provide a detailed discussion of the planning
approach and discuss the determinative reasons (i.e.
the main reasons why the applicant chose a particular
route) for selecting the configuration of the proposed
corridors. For example, "the corridor bears west
at mile #33 in order to avoid encountering a TV tower
between a wetland area and residential area in mile
#34"). This could be done as a table keyed to the
route delineation maps, or indicated on the maps
themselves.
Identify major alternative corridors which have
been considered. If proposed (rather than existing)
substations are used as defining points for corridor
location, describe the reasons the substations have
been proposed for their specific locations, and the
degree of flexibility of those locations should
corridor siting in that area become a problem. Describe
the determinative reasons for discarding alternative
corridors in favor of the proposed corridor(s).
2.2
Socio-Political Environment of the Corridor Area
2.2.1 Governmental Jurisdictions
Provide maps of at least 1:126,720 scale
indicating the city limits of municipalities crossed by
the corridor. Identify all of the following local,
regional, federal or state areas through which the
corridor will pass or to which it will come within
one-mile: National Parks, Forests, Seashores, Wildlife
Refuges, Wilderness Areas, Memorials and Monuments or
other properties listed in the National Register of
historic Places, or as National Landmarks, Marie
Sanctuaries, Estuarine Sanctuaries; RARE (Roadless Area
Review and Evaluation) Areas, State Parks, Forests,
Game Management Areas, Areas of Critical State Concern,
Conservation and Recreation Lands, State Archaeological
Landmarks or Landmark Zones, Aquatic Preserves,
Outstanding Florida Waters, county parks or special
management areas established by law; Indian
Reservations and military landholdings.
2.2.2 Zoning and Land Use Plans
Identify local government comprehensive plans
adopted pursuant to Ch. 163 F.S. for the jurisdictional
area in which the corridor is located. Where
comprehensive plan land use maps are available and
reproducible, attach and indicate the location of the
corridor in relation to the land use plan categories;
otherwise, provide an approximation of the same.
Provide a description of each known applicable land use
category, an identification of each affected zoning
district, and each district's land use restrictions
(for example, noise ordinances, vegetative screening
requirements, height limitations, setbacks from other
structures, etc.). Indicate any variances, exemptions,
or exceptions in land use plans or zoning ordinances
that the applicant knows may be necessary to allow for
the construction of this project. if lengthy, the
information requested above may be provided as an
appendix.
2.2.3 Easements, Title, Agency
Works
Identify the easements, licenses, or other
interests in State lands which are necessarily for
construction of this project. Also, if known, identify
1) the proposed locations for which the utility would
traditionally been required to request road, pipeline
or waterworks crossing approvals from State, regional
or local governments, 2) rights-of-way which will be
crossed, and 3) any changes which may be necessary in
such roads, canals, etc., to accommodate traversement by
the transmission lines. This may be done in the form of
a chart as illustrated in Figure 1.
2.2.4 Archaeological and Historic
Sites
Indicate whether or not the corridor will
traverse any known archaeologically or historically
significant sites or areas considered to be potentially
sensitive, archaeologically or historically, above or
below water, as identified by the Department of State,
Division of Archives, History and Records Management
(DAHRM). Significance will be determined pursuant to
the criteria presented in 36 C.F.R. 63
"Determinations of Eligibility for Inclusion in
the National Register of Historic Places".
Describe the methods used in making archaeological and
historical studies of the corridor. Methods should be
acceptable to the DAHRM. Copies of reports resulting
from such surveys should be submitted to DAHRM.
2.3
Bio-Physical Environment of the Corridor Area
2.3.1 Land Use/Vegetation
For the area of the corridor and extending
one-half mile from each edge of the corridor, provide
aerial photographs of at least 1:24000 scale,
preferably 1:12000.
On a map of 1:24000 scale or greater covering the
same area as the aerial photographs, indicate the
existing land uses. Also, indicate all types of
vegetation occupying areas five acres or more for the
area of the corridor and for an area extending one-half
mile from either edge of the corridor where
vegetational information is readily available; where
the applicant must develop its own vegetation maps, an
area extending one-quarter mile from either edge of the
corridor will be accepted. If the applicant uses
1:24000 scale aerial photographs or any size less
specific than 1:12000, then for areas on the land
use/vegetation maps which occupy less than five acres,
identify whether each area is vegetated rather than
barren or altered by man. Use at least Level II
categories of the "Florida Land Use and Cover
Classification System: A Technical Report" to
depict land use, and Level III categories for
vegetation.
2.3.2 Affected Waters and Wetlands
Characterize any surface water bodies or wetlands
which are crossed by the corridor. Include a general
description of significant drainage features or
drainage patterns (such as sheetflow) which may be
affected by the ROW and access roads. Indicate the
water classification designated in Florida
Administrative Code Rule Chapter 17-3.
2.3.3 Ecology
Identify any species which are endangered,
threatened, or species of special concern which may
reasonably be expected to be affected by the proposed
facility. Also, other unique situations may be
identified through the scoping process for review and
impact assessment. A species which is endangered,
threatened, or species of special concern is any
species officially designated as such by the U.S. Fish
and Wildlife Service or Florida State agencies such as
the Game and Fresh Water Fish Commission. The applicant
should establish with DER and the GFWFC the species to
be studied.
Map or otherwise identify the location of known
occurrences of the species studied and habitat
features critical to endangered and threatened species
(e.g., bald eagle nests) in the corridor and 1500 feet
beyond either edge of the corridor, preferably on the
land use/vegetation maps.
Describe the methods used to determine the
species locations. Sources of information should be
identified. Studies in progress should be noted and
described.
2.3.4 Other Environmental Features
Where relevant information on the corridor
environs does not fall clearly within the scope of the
preceding topics, additional information which may be
necessary to adequately describe the corridor should be
included here.
Figure
1. Sample Chart for Identification of
Easements, Title, or Agency Works Which May be Affected
by Project Construction
| Facility |
Affected
Agency |
Type
Previous Approval |
Potential
Changes |
| Marion
County |
|
Highway 237 |
Fla.
DOT |
Crossing
Easement |
None |
|
Cross Marco Barge Canal |
TIITF |
Title |
Bridge
Construction |
| Oklawaha
County |
|
Canal 36 Water Control Structure |
St.
James Water Management District |
Crossing
Easement |
Widen
Weir Road to 14 Feet |
CHAPTER 3
Effects
of Right-of-Way Preparation and Transmission Line
Construction
The expected effects of the preparation of the
right-of-way and the construction of the transmission
line are to be provided in this Chapter. The effects
should be presented in terms of their physical impact
on the resources and populations described in Chapter
2.
In the applicant's discussion of environmental
effects, it should be made clear which of these are
considered unavoidable and irreversible. Those effects
which represent an irretrievable commitment of
resources should be discussed where appropriate under
each category. In the context of this discussion,
"irretrievable commitment of resources"
alludes to natural and cultural resources and means a
permanent impairment of these resources, e.g., loss of
wildlife habitat, impairment of nesting, breeding or
nursery areas, interference with migratory routes,
damage to archaeological or historic sites, loss of
valuable or aesthetically treasured natural areas, as
well as the expenditure of directly utilized resources.
Mitigative measures to reduce or eliminate impacts
should be discussed where appropriate under each
category.
3.1
Construction Techniques
Provide detailed information concerning typical
construction techniques for the towers, foundations,
road construction, and types of equipment to be used on
this project. Discuss potential erosion problems which
might be caused by construction, and indicate any
mitigative measures that are proposed.
3.2
Impact on Waterbodies and Uses
3.2.1 Preliminary Assessment Data
For those areas where the applicant is unable to
provide detailed information on dredging and filling
which may be associated with the project prior to
certification, provide the information listed below.
Detailed information as identified in section 3.2.2
will be required to be submitted after certification.
Discuss the impact of ROW preparation and construction
activities on affected waters, and identify in which
watercourses or wetlands the applicant believes
construction will occur in or may affect. Describe
activities which may affect water flow (including
sheetflow) such as the construction of cofferdams,
dredging operations, borrow pits, the placement of
culverts or fill material, etc. It is recognized that
certain activities may be required in one part of the
corridor but not the other, however, it is the intent
of this requirement to ascertain such facts. Describe
the effect of these activities on navigation, water
quality and water quantity. Discuss any proposed ground
or surface water impacts such as withdrawals,
dewatering, temporary realignment of streams during
construction, new connections to waters of the State,
etc.
If filling is anticipated for road beds, structure
pads, etc., provide a typical cross section and plan
view. In areas where data is available, indicate in
which waters keyhole filling may reasonably be used in
lieu of continuous fill. For water bodies in which
water flows in a defined bed or channel, such as
incised streams, rivers, etc., with little or no
associated floodplain, indicate where applicable,
gauged streamflow information is available. (Generally,
this information will be limited to data within three
miles of any known crossing site or two miles of the
corridor if specific locations are not known at the
time of application filing.) Indicate how many points
of low input there are between the potential
construction site or corridor and the identified
gauging station. Provide an estimate of the drainage
area input between the proposed construction area or
corridor and the gauge.
Discuss measures designed to mitigate the impacts
outlined above.
3.2.2 Actual Site Data
3.2.2.1 Generic Data
When generic information is to be submitted, it shall
consist of the following:
(a) A map locating the construction
within a county and a map identifying each specific
dredge and fill site on U.S.G.S1:24,000 quadrangle
sheets. A designation code may be assigned by the
applicant for each specific potential dredge and fill
site. An example of a designation site would be
"BRO-1" for the first dredge and fill site in
Broward County; "BRO-2" for the second dredge
and fill site in Broward county; and accordingly with
all other dredge and fill sites in Broward County.
(b) Legible and reproducible standard
plan and profile view 8 1/2" x 11" drawings
which have been certified by a professional engineer or
signed in accordance with Chapter 473, Florida
Statutes.
1. The drawing(s) shall indicate:
a. The name of the water, if any.
b. The estimated width of the
waterway showing the estimated limits of the state's
jurisdiction.
c. The direction of flow or ebb and
flood.
d. The north arrow.
e. The general contour of the natural
ground.
f. Typical structure placement.
2. The drawing(s) shall depict the standard
installation of a culvert.
3. The drawing(s) shall depict each type of
structure pad indicating the dimensions for each type
of structure pad, including height above upland natural
ground, side slopes, length and width.
(c) Data in one of the following
forms unless otherwise altered in accordance with FAC
Rule 17-17.60(4):
1. U.S.G.S. or other gauged information on
streamflows, whenever existing data is available within
close proximity (generally less than three miles) to
any proposed site. Indicate how many points of flow
input and drainage area input there are between the
proposed site and the gauging station; or
2. Water volume calculated using the Soil
Conservation Service (SCS) method for each non-gauged
or measured watercourse or wetland site where existing
measured data is not available. A 1-in-25 year storm
event and the hydrologic group classification of the
soils in the area as taken from the Soils Indication
List currently being utilized by the SCS shall be used
in the water volume calculation unless otherwise agreed
to by the applicant and the department. A calculation
methodology different than the one provided in this
subsection may be used if agreed to by the department
and the applicant; or
3. If required by the conditions of
certification, existing stream flow system measurements
in waters which flow in a defined bed or channel
(incised streams, rivers, etc., with little or no
associated floodplain). Generally, this requirement
would be met by providing data on the waterbody
cross-sectioned bank to bank, the velocity at a number
of specified points, and would be performed once a week
for a period of one year or as otherwise agreed by the
department. Volumetric calculations could be made from
these flow measurements.
(d) The following information shall
be required and may be presented on a data sheet in
conjunction with the data required in (c):
1. The number and capacity (total square
footage) of the culvert(s) to be used. This capacity
should be capable of handling the calculated water
flow. When the capacity is based on Soil Conservation
Service methods of calculation, a stipulation may be
necessary to require resizing of the culverts if actual
measurements performed at a later date indicate the
need for greater capacity.
2. The placement of the culvert(s) and the
maximum spacing between culverts.
3. Elevation of the culverts and road; this
may initially be presented with the bottom of the
waterway identified as an elevation of 0.0 feet, but
prior to construction, elevations referenced to NGVD or
other reference point shall be submitted. The elevation
information may be submitted in the form of a data
sheet or by revising the previously submitted drawings.
This other reference point may be an informally
established point such as a relatively permanent and
clearly identifiable landscape feature. Whenever
informally established reference points are used in
lieu of NGVD data, a relatively permanent and clearly
identifiable landscape feature must be used and
identified in information submittals. An example of
such reference point would be a stake with a pin on top
driven in the ground a certain distance from the edge
of the right-of-way )so that construction equipment
does not inadvertently obliterate it).
4. Peak discharge velocity (may be a part
of (c)).
5. Width of the waterway at the point of
crossing during normal high water.
(e) an aerial photograph on a scale
of 1"=600' or greater detail scale, indicating the
location of each potential dredge and fill site.
(f) A statement on the construction
techniques to be used by the applicant in order to
comply with all applicable laws including type and
source of fill to be used, stabilization techniques,
clearing techniques, turbidity control techniques, type
of equipment to be used, and techniques to prevent
funneling.
3.2.2.2 Specific Data
When specific information is to be submitted, it shall
include, at a minimum, the following:
(a) Same as 3.2.2.1.(a). Also,
structures shall be separately coded, i.e., each tower
shall have a reference number which will be used in all
certification correspondence.
(b) Same as 3.2.2.1.(b) as well as:
1. The specific location and design
of all access roads, structure pads, water control
structures (culverts, weirs, etc. and elevations of
these features in reference to NGVD.
2. Cross-sections of each waterbody
at the point to be crossed by access roads.
3. The foundation work for any
structures to be free-standing on waterbodies.
4. Spoil disposal areas for any
dredging work done, including removal of tree roots.
(c) Same as 3.2.2.1.(c) - (f).
3.3
Solid Wastes
Describe the anticipated type and quantities of
solid waste that will result from right-of-way
preparation and transmission line construction.
Describe the methods and locations of disposal.
3.4
Changes to Vegetation, Wildlife and Aquatic Life
Discuss the impacts of construction such as any
permanent changes that will be induced in the physical
and vegetation, aquatic life, or wildlife, particularly
endangered or threatened species, identified in section
2.3.3, through changes in hydrology, ground cover, or
the construction itself. These changes may include loss
or increase of wildlife habitat, impairment or
improvement of nesting, breeding or nursery areas,
interference with migratory routes, etc. Describe how
these conclusions were reached. Indicate any mitigative
measures designed to minimize adverse effects.
3.5
Impact on Human Populations
Identify undesirable impacts on proximate human
populations arising from construction noise or
inconveniences due to the movement of personnel,
materials, or machines.
3.6
Impact on Archaeological and Historic Sites
Discuss construction impacts on archaeological
and historic sites deemed significant in 2.2.4,
including those significant sites recommended for
preservation. Describe what action is being proposed to
mitigate these impacts. Discuss the procedure to
identify, catalogue and preserve unforeseen discoveries
of archaeological sites until their significance can be
determined.
CHAPTER
4
EFFECTS
OF TRANSMISSION LINE RIGHT-OF-WAY MAINTENANCE AND
POST-CONSTRUCTION IMPACTS AND EFFECTS OF MAINTENANCE
The interaction of the transmission lines, access
roads, and rights-of-way with the environment are to be
described in this chapter. The applicant is not
required to repeat the material presented in Chapters 2
and 3, but such previously presented material should be
cross-referenced.
4.1
Maintenance Techniques
Discuss maintenance techniques which may be used
along the right-of-way: whether burning will be used,
how often, and if fire lanes will be necessary; whether
herbicides will be used, and if known, the expected
types, volumes, concentrations and frequency of use;
the types of cutting, chopping, or mowing equipment to
be used and frequency of use; whether soil seeding and
fertilization will be done; whether techniques will be
used to control the vegetative species to enhance use
of the corridor by local biota; and, the effects of
maintenance techniques on plant life and wildlife
habitat.
4.2
Multiple Uses
Describe what kind of multiple uses, if any, such
as truck or citrus farming, will be allowed in utility
owned or controlled rights-of-way.
4.3
Changes in Species Populations
Discuss changes in the population of species
identified in section 2.3.3 which may be caused by the
maintenance of the right-of-way, with the view of
determining whether these changes represent long-term
net loss or gains. If a change is expected, then
provide the reasoning for the expectation.
4.4
Effects of Public Access
If access roads increase the exposure of
previously undisturbed areas to the public, discuss the
potential effect of this increased exposure on wildlife
or environmentally sensitive areas. Describe controls
planned to reduce these impacts.
4.5
Electric and Magnetic Field Effects
Describe the electromagnetic fields generated by
the lines and their strengths and extent. Provide a
depiction of the expected field compared to distance
horizontally along the right-of-way under the
conductors, and perpendicular to the centerline of the
right-of-way laterally under the lines until
attenuation to a level of 1 kilovolt/meter is reached.
Unless the department has an adopted rule
addressing the topics listed below, or unless such rule
requires otherwise, provide the following information:
Biological Effects -- Discuss the potential for
effects from electric fields as they may affect health
and the environment along the transmission line
rights-of-way. Briefly summarize the current status of
research on biological effects of electric and magnetic
fields.
Noise -- Discuss the potential for acoustic and
electrical noise from electric and magnetic fields,
including shadowing and reradiation, as they may affect
health or communication systems along the transmission
rights-of-way. Indicate the noise level generated by
the line in both dB and dBA scales and compare this to
any known noise ordinances for the zoning districts
through which the transmission line will pass.
Safety -- discuss the potential for induced or
conducted currents along the transmission line
rights-of-way from electric and magnetic fields. State
whether compliance with the applicable sections of the
National Electric Safety Code will be achieved.
Describe the purpose of the Code as it relates to
public safety.
CHAPTER
5
VARIANCES,
EXCEPTIONS, EXEMPTIONS
List each variance, exception, or exemption from
applicable state and local standards, land use plans,
or zoning ordinances which the applicant knows at the
time of application filing will be sought as part of
the certification. Cite the code section number for the
standard for which the variance, exception, or
exemption is sought. State 1) the nature of the
variance, exception, or exemption, 2) the reason for
seeking it, 3) the anticipated renewal periods, and 4)
facts that show a variance, exception, or exemption
should be granted.
For environmental variances to obtained from the
department, provide the information required by
subsection 17-103.100, FAC, including a statement
identifying the nature of quality control information
on all sampling data submitted and where it may be
obtained by the department. The justification for
granting a variance shall include an analysis of all
alternatives considered, including costs, and any other
information which would clearly demonstrate that the
variance should be granted.
|