Florida Department of Environmental Protection Florida Department of Environmental Protection
More Protection, Less Process
* DEP Home * About DEP * Programs * Contact * Site Map * Search
MyFlorida.com  
Power Plant Siting Overview Highlights

General Information

Pre-application Activities

Certification Process

Post-certification Process

Process Flowchart 

 

General Information

Note: What follows is a plain language description of the Power Plant Siting process.  It should not be considered a substitute for the applicable Statutes or Rules. Should differences exist between this description and a Statute or Rule, the Statute or Rule is to be considered as over-riding and correct.

The Power Plant Siting Act (PPSA), ss. 403.501-.518, F.S., is the State’s process for the licensing of large power plants.  A certification constitutes the sole license of the state and any agency as to the approval of the location of the site and any associated facility, as well as the construction and operation of the electrical power plant, except for the issuance of licenses required under any federally delegated or approved permit program and any other exemptions provided in 403.511(4). The PPSA was designed to provide a streamlined process for the development of energy infrastructure, which is necessary for the health, welfare, and protection of the citizens of the state, while protecting the public and the environment from the impacts of the infrastructure.  While most facilities need to get any number of permits or approvals from local and state agencies, large power plants in the State are treated differently.  All local and state permits or approvals are pre-empted, and only one license is issued, called a “certification”.  However, all of the local governments or state agencies within whose jurisdiction the power plant is to be certified participate in the process, to assure that the issues normally subject to regulatory approval or other authorizations are addressed.  Therefore, the PPSA is a centralized licensing process encompassing the permitting, land use and zoning, and property interests of all state, regional, and local agencies which have jurisdiction over an area where an electrical power plant is or potentially will be located.

        The Act was revised by the 2008 Legislature in order to further streamline and provide distinct timeframes for the hearing provide, while at the same time and provide increased opportunities for public interaction.  This webpage is undergoing revision to incorporate the changes made.

        Ch. 62-17, Part I, (62-17.011 - .62-17.293), Florida Administrative Code, is the procedural Rule implementing the PPSA.  This rule is currently under review for changes necessary to reflect the 2006 Legislative revisions.   Note that only Part I pertains to Power Plant Siting. The Application Guide is also available electronically.  This "guide" is a narrative resembling the requirements for an Environmental Impact Statement, and indicating the nature of the information which must be provided, but is not a "fill-in-the-blank" type form. As with Ch. 62-17, Part I, the guide is under review for updating.

        The PPSA provides for certification of any electric power plant as defined in 403.503(14), which generates 75 megawatts (MW) or more in capacity, and was constructed after October 1, 1973. The Act applies to nuclear power in addition to coal, gas, and waste to energy facilities, although certain licensing functions are preempted by the federal government. Power plants may have operational lives of 40 or more years, and certification is a “life-of-the facility” approval.

        Certification may include a power plant's associated facilities. Such facilities are those which are necessary (either directly or indirectly linked) for the construction and operation of the power plant, such as a natural gas pipeline supplying the plant's fuel, rail lines for bringing in coal to the site, roadways, and the electrical transmission lines carrying the power to the electrical grid, among others. These facilities may be located both onsite and offsite of the electrical power plant facility.  For linear features, the applicant can propose certification of a corridor, within which a right-of-way will be located.  The applicant can propose multiple alternate corridors for certification as well, in order for the public to have knowledge of multiple potential possibilities. These corridors can be up to a mile in width, whereas the rights-of-way are typically more on the order of 100-200 feet in width, depending on the facility type.

        Certification is issued by the Siting Board (Governor & Cabinet), or, under the revised law, by the Secretary of DEP on behalf of the Siting Board in non-contested case.  In either instance, DEP is the lead agency for coordination of the siting process, and has its own jurisdiction for many of the activities which the certification is in lieu of, just like any other agency.  Thus, it wears "two hats".  One is for the coordination role and supporting the "Siting Board" --- this task has been assigned to the Siting Coordination Office (SCO), with legal support from the Office of General Counsel. The other "hat" is for its standard jurisdiction, including wetlands permits, state lands oversight, coastal protection, and so forth, as administered by the other Divisions and District Offices of the Department.  The SCO also internally coordinates with federally approved or delegated permit program matters that may affect the certifiability of the proposed power plant.

        The Act was created by the Legislature in 1973, leaving many older power plants in use in the state licensed under regular permitting rather than the PPS-certification.  Some sites have generation units which were permitted prior to the passage of the Act, and some after, so different procedures and coordination contacts may apply for the same site's differing units.   See the "Power Plant/Transmission Line Siting Status Chart" for a listing of those units or sites which fall under the PPSA. 

        The PPSA allows the filing of applications for:

  • a site and several units to be constructed commencing upon certification

  • alternate corridors for related facilities at the option of the applicant

  • a site at which one or more units will be constructed commencing upon certification, and the others will be constructed some time in the future ("ultimate site capacity")

  • supplemental units to be added to a site which has been certified for "ultimate site capacity"

  • certification of a power plant site existing prior to the creation of the Power Plant Siting Act at which the utility wants to make changes which will result in an  increase in generating capacity, or at which the applicant wants to roll all existing individual permits into a unified certification.

      Since certification is a life-of-the facility authorization, the considerations involved in the application review are extensive, and the applications themselves may be many volumes in size.  The application process for a new facility is discussed below, and should provide guidance on how the statutes and rules interweave, and who is responsible for what tasks.  The process for supplemental units at the same site, or certification of an existing site is quite similar, albeit with a few omitted steps or with shorter timeframes.  A modification process is provided for in the PPSA (see further below) to accommodate the numerous changes that may occur during the operational period.

      Electric Utilities are allowed to obtain separate licenses, permits, or approvals for certain pre-construction infrastructure without first obtaining certification under this act if the utility intends to locate, license, and construct a proposed or expanded electrical power plant that uses nuclear materials as fuel. These facilities may include access and onsite roads, rail lines, electrical transmission facilities to support construction, and facilities necessary for waterborne delivery of construction materials and project components. This exemption applies regardless of whether the facilities will be used in operation of the power plant. The applicant has to keep the Department of Environmental Protection up to date on necessity of these facilities for construction of the power plant, and the status of these applications.  Any approvals or permits provided to the utility for these facilities will be incorporated into the certification of the power plant. The facilities may be located on or offsite of the proposed power plant.


        Note: For those interested in following long-range planning for power plants, The Public Service Commission (PSC) oversees the submission of “Ten-year Site Plans” (TYSPs) by the utilities.  The plans describe current generation capacity and anticipated need for more capacity.  The TYSPs also provides generic information on future sites for power plants to accommodate the anticipated need. This information includes land use data, environmental factors, and similar topics which allows other state and local agencies to comment on the Plans to the PSC.  These comments may range from suggestions on how to improve utilization of the site, and on site problems, to recommendations that the site not be considered at all for various reasons.  Based on this information and its own conclusions, the PSC will determine the suitability of the plan and issue an Annual Review (2007 Review). 


 

  I.  Pre-application filing activities    

A.    Notice of Intent 403.5063

        A potential applicant may elect to file a Notice of Intent (NOI) to indicate that it plans to submit an application, and then work with the reviewing agencies on what information should be included in the application.  If a NOI is to be filed, this must be done at least 6 months prior to application filing. Although the NOI process is a formal activity, pre-application discussions of the same nature typically occur informally.       

B.    Need Determinations

        Need Determination is a formal process required under s. 403.519, F.S., and is conducted by the Public Service Commission (PSC).  The PSC reviews the need for the generation capacity which would be produced by the proposed facility in relation to the needs of the region, and to the state as a whole.  The PSC also looks at:

  • the need for electric system reliability and integrity,

  • the need for adequate electricity at a reasonable cost,

  • the need for fuel diversity and supply reliability,

  • whether the proposed plant is the most cost-effective alternative available,

  • the conservation measures taken by or reasonably available to the applicant or its members which might mitigate the need for the proposed plant,

  • other matters within the PSC’s jurisdiction which it deems relevant.

        If the proposed power plant will use nuclear materials as fuel, the PSC must look at matters within the PSC’s jurisdiction which it deems relevant, including whether the nuclear plant will:

  • Provide needed base-load capacity.

  • Enhance the reliability of electric power production within the state by improving the balance of power plant fuel diversity and reducing Florida's dependence on fuel oil and natural gas.

  • Provide the most cost-effective source of power, taking into account the need to improve the balance of fuel diversity, reduce Florida's dependence on fuel oil and natural gas, reduce air emission compliance costs, and contribute to the long-term stability and reliability of the electric grid.

        The Need Determination process can occur prior to the filing of a certification application, or afterwards; however, it is usually recommended that it be commenced beforehand. An applicant is required to have an affirmative determination of need from the PSC in order to obtain a certification.

        If the PSC makes a negative determination prior to the submittal of the certification application, or recommends that an alternative approach is more suitable, then either the pending application will not be submitted, or should be revised.  If the application has already been submitted, and the PSC makes a negative determination, then the certification application process comes to a halt.

C.    Federally Delegated or Approved Permits

        As noted above, PPSA certification pre-empts all State and local government permitting requirements.  However, permits that the DEP administers pursuant to federal permit programs are handled separately from PPSA certification, and those separate federal permits must still be issued. Submittal of applications for these permits can occur prior to the filing of a certification application, or afterwards; however, it is recommended that they be submitted prior to the certification application.  These permits are integral to the authorization for construction and operation of a power plant.  Currently, these permits are the:

         The review of these permits is ongoing at the same time the certification process, but does not operate under the same time schedules as certification. (Note: The splitting of the review of these permits out from under the certification process “umbrella” was a change in the 2006 Legislation. The reason was to delete conflicts between the procedures and authorities for the permits and PPSA.) In the instance of disputes regarding these permits, petitions for hearings are handled independent of the certification process. However, to facilitate coordination between these integral aspects of a power plant review, when possible, any hearings may be conducted in conjunction with the administrative hearing on certification.  The final approval body for federal permits is not the Siting Board, but the Department of Environmental Protection via its authority granted by the US Environmental Protection Agency. In the remainder of this discussion, unless otherwise specified, use of the term "application" and the procedures outlined refer to the certification side of the process.


 

 II.  Certification Process  

 

 (See also flowchart)  [It is recommended that the reader print out the flowchart to better follow along with the process described below]

         In the application review process, there are initially five “tracks” that commence once the application is filed (see flowchart).  These “tracks” are (a) the “application completeness determination” process, (b) the “Informational Public Meetings”, (c) the “Local Government Consistency Determination”, (d) “Need Determination” process which was previously described, and the (e) “Federally Delegated or Approved Permit” review process, which was previously described.  Eventually these tracks merge at varying points.

         A.  Application Filing and Distribution 403.5064   

         The application must be submitted along with the appropriate fee in order to initiate the review process.  The initial distribution is to the DEP’s Siting Coordination Office (SCO) and statutorily named agencies**. Other agencies may later be requested to review the application as well. The application is supposed to contain all information that would otherwise be required by the individual agencies to obtain regulatory permits, authorizations, or proprietary usage permissions. [**Department of Community Affairs, Fish and Wildlife Conservation Commission, Department of Transportation, the jurisdictional Water management District(s), the jurisdictional Regional Planning Council(s), the jurisdictional county(s) and the jurisdictional city(s).]

           The applicant may also include a statement affirming that the applicant has opted to allow consideration of alternate corridors for an associated transmission line corridor. If the applicant chooses this option the portion of the application addressing associated transmission line corridors is processed under the schedule set forth in F.S. 403.521-403.526, 403.527 (4), and 403.5271, including the opportunity for the filing of alternate corridors by 3rd parties. Filing of alternate corridors will not result in the rescheduling of the certification hearing.

          When possible, a copy of the application will be published to the Siting website.  See "Applications in Process".

         Once an application has been properly filed, the DEP Office of General Counsel's Siting attorney will request the assignment of an Administrative Law Judge by the Division of Administrative Hearings (DOAH). This immediately shifts the review into a formal litigation proceeding, requiring assistance from legal staff at the outset, including legal staff from all the agencies.  DOAH assigns a Docket number to the case, and information about legal filings can be found on DOAH’s website. A link to the Docket can be found on the “Applications in Process” website described above.


Note to Agencies regarding Fees: Under the PPSA, agencies required to prepare reports, or which were requested to prepare reports are eligible for reimbursement of agency expenses on the project from the fee (up to a limit based on the fee amounts available; if available amounts are insufficient, then a pro-rata disbursement will be made). Additionally, under the Power Plant Siting Act the unexpended portion of the fee reserved for the affected agencies is refunded if the application is withdrawn. Therefore, the staff of all the affected/reimbursable agencies are encouraged to track their time and expenses from the beginning of the process.  (Refer to s. 403.518(2)(c), F.S., and Ch. 62-17.293, F.A.C.)


   

        Within 21 days of the application filing, notice must be published about the application.  The applicant is required to have a newspaper notice is required that must be at least 1/2 page in size; often, these are as large as 1 to 2 pages in size.  The DEP must have notice published in the State’s Official notice publication site, the Florida Administrative Weekly (F.A.W.). 403.5115

         The newspaper notice will contain a map of the proposed project, including any associated facilities, briefly describe the process, and provide information about becoming Parties to the proceeding.

          B.  Public Involvement and “Parties to the Proceeding

         Entities and persons that are affected by the proposed project may become involved in the process in two types of roles:  one is simply as a “person”, who can attend the hearings and provide comments on their own behalf, and the other is as a “Party”.  There are several requirements for becoming a Party to the Proceeding, and responsibilities associated with this role.  Parties typically are represented by attorneys, must exchange copies of legal filings with each other, and may cross-examine witnesses at the hearing.  There are deadlines for becoming a Party to the certification proceeding, as follows:

  • Certain state, regional and local agencies [see s. 403.508(3)(a), F.S. for a complete list] are automatically parties , but will waive their rights to remain as parties if they fail to file a notice of intent to be a party by the 90th day prior to the certification hearing, so long as they file a notice on intent with the Administrative Law Judge to this effect.

  • An agency not named in the statutory list above, or non-profit organizations formed for specific purposes** can file a notice of intent to be a party with the Administrative Law Judge, but this must be done no later than 75 days after the application was filed.  [**These groups can be “Any domestic nonprofit corporation or association formed, in whole or in part, to promote conservation or natural beauty; to protect the environment, personal health, or other biological values; to preserve historical sites; to promote consumer interests; to represent labor, commercial, or industrial groups; or to promote comprehensive planning or orderly development of the area in which the proposed electrical power plant is to be located”.]

  • Any person/entity who has not filed a notice intent to be a party by the deadlines identified above but who can demonstrate that the project substantially affects them may be allowed by the Administrative Law Judge to become a Party, but this request to intervene must be submitted to the Administrative Law Judge no later than 30 days before the commencement of the certification hearing.

         C.  Completeness 403.5066

         Once the certification application is filed, the DEP/SCO determines whether or not the application is "complete". This is a determination of whether the information provided by the applicant is adequate for agencies to analyze the impacts of the proposed project and compliance with applicable regulations. This determination is based on the recommendations of the affected agencies and the appropriate staff in DEP’s Bureaus and Divisions. These recommendations are due to the SCO within 30 days of the application filing. The completeness determination must occur within 40 days of application filing.

        To simplify the completeness review, DEP recommends that the agency’s issues be broken down by subject area and/or geographical area. Some examples are:

                 Local Government:

  • Associated facility corridor – corridor delineation not precise enough to determine whether there may be an impact on “xx” City Park.

  • Primary site – Land Use Plan information out of date with regards to ordinance on facilities adjacent to the Regional Airport.

                     Water Management District:

  • Primary site – Water Quantity information -- Wellfield pumping proposal does not show impacts out to “xx” miles from the draw-down core.

  • Associated facility corridor –Application does not include information regarding proprietary use of the “XXX” water control levee.

*           If the application is not complete, the applicant may submit additional information, withdraw the application, or contest the determination. If the applicant elects to submit additional information, another completeness determination is made.  Two options for timing of the additional information submittal exist. 

                 (1)   If the applicant submits the information within 30 days of the initial completeness determination, then the affected agencies have 15 days from the filing of additional information in which to review the supplemental information and submit recommendations as to completeness.  The second determination by DEP must be issued within 22 days of the supplemental information submittal.  If the application is determined complete at this time, the process continues on with no tolling (halting) of the clock [unless it has otherwise been halted by certain events in the Land Use Consistency determination portion of the process, explained further below].  The process does not provide a direct role for public comment in the completeness review process, however, the public is welcome to submit concerns to the agency with jurisdiction over the matter of concern for inclusion in that agency’s comments if it feels the item to be applicable.

                 (2)  The applicant may indicate that it needs more time than 30 days to submit the initial determination.  In this instance, the time frames in the process are halted until the application is determined complete via the completeness review process and timing described above.

         If the applicant elects to contest the determination, the applicant files a petition with the Administrative Law Judge (ALJ), who will schedule a hearing on the matter, to be held within 21 days of the determination of completeness.  DEP, the applicant, and the jurisdictional agency whose data needs are at issue are the parties to this hearing.

          D.  Land Use Determination 403.50665  

Within its application, the applicant includes a statement on the consistency of the site or any directly associated facilities that constitute a development as defined in F.S. 380.04, with existing land use plans and zoning ordinances that were in effect on the date the application was filed. This information includes an identification of associated facilities the applicant believes are exempt from the requirements of land use plans and zoning ordinances. This requirement does not apply to new electrical generation units being proposed for construction and operation on the site of a previously certified electrical power plant or on the site of a power plant not previously certified that will be wholly contained within the boundaries of the existing site.

        Unless exempted as per above, forty-five days after the filing of the application (and shortly after the first completeness determination is issued), each local government within whose jurisdiction the site and any associated facilities are located is required to file a determination on the consistency of the proposed project with their land use plans and zoning ordinances. A copy of this filing must be provided to DEP, the ALJ, applicant, and all parties.  If the local government has raised completeness issues that affect their determination, they can postpone issuing the land use determination for 55 days [note: due to space limitations, this delay is not depicted on the flowchart].  Special Information for Local Governments

         No later than 21 days after the issuance of each determination, the DEP must have Florida Administrative Weekly notice published regarding each determination must be published, and the applicant must have published a half-page newspaper notice (minimum size) of each determination.

         The determinations are subject to dispute by persons who are substantially affected by the determination. It is likely that this would only occur with a finding of consistency. If the finding is of inconsistency, the applicant also has an avenue of relief (described below).

          If the initial determination of the local government is that the power plant site or associated facility is inconsistent, the applicant can go back to the local government with a revised proposal intended to be consistent, the same as if the Siting Board has ratified a determination of inconsistency, as described above.  Similarly, while this is ongoing, all other parts of the application review process comes to a halt.  The local government must review the revisions, and issue another determination. The determination can either be that the facility in question is either consistent or inconsistent, but either way, newspaper notice and F.A.W. notice must again be published, and the steps/options outlined above repeated. The local government must commence a proceeding to consider the application for land use or zoning approval within 45 days after receipt of the complete request and will issue a determination within 30 days following the conclusion of that local proceeding.

           If any substantially affected person wishes to dispute the local government’s determination, they must file a petition petition stating the basis of the dispute must be filed with designated administrative law judge no later than 21 days after the publication of the latest-date notice for that particular determination –- either the newspaper notice or the F.A.W. notice, whichever comes later. 

            The dates regarding the land use consistency determination may be altered upon agreement between the applicant, the local government, and the Florida Department of Environmental Protection.

            The issue of land use and zoning consistency for any proposed alternate intermediate electrical substation which is proposed as part of an alternate electrical transmission line corridor (which is accepted by the applicant and the department under 403.5271(1)(b), must be addressed in the supplementary report prepared by the local government on the proposed alternate corridor. It will be considered as an issue at any final certification hearing. If such a proposed alternate intermediate electrical substation is determined not to be consistent with local land use plans and zoning ordinances, that substation will not be certified.

Land Use Hearings 403.508(1)

Within 5 days of a petition for a hearing on land use has been filed pursuant to s. 403.50665, the designated Administrative Law Judge will schedule a hearing to be held in the county of the power plant or associated facility, as soon as possible, but no later than 30 days after the filing of the petition.  If there are several disputes in one county, there will be one hearing, but if there are disputes in multiple counties, there may be multiple dispute hearings.

The sole issue for determination at the land use hearing is whether or not the proposed site or nonexempt facility is consistent and in compliance with existing land use plans and zoning ordinances. If the administrative law judge concludes that the proposed site or nonexempt facility is not consistent or in compliance with existing land use plans and zoning ordinances, the administrative law judge will receive evidence on, and address in the recommended order any changes to or approvals or variances under the applicable land use plans or zoning ordinances which will render the proposed site or nonexempt facility consistent and in compliance with the local land use plans and zoning ordinances.

 For each hearing, there will be Florida Administrative Weekly notice published by DEP, and a half-page (minimum size) newspaper notice published by the applicant.  Within 30 days of the conclusion of the hearing(s), the ALJ will issue a Recommended Order.  Within 60 days after receipt of the proposed Order, the Siting Board (Governor & Cabinet) must rule on whether or not the determination will stand.

          The Siting Board’s decision settles the dispute, whether by ratifying a determination of consistency, or by issuing a variance overriding the plan or ordinance that is inconsistent.  If the Board ratifies the determination of inconsistency, the applicant can go back to the local government with a revised proposal intended to be consistent, but while this is ongoing, all other parts of the application review process comes to a halt. The Siting Board can also provide a variance or other necessary approval to the adopted land use plan and zoning ordinances required to render the proposed site or associated facility consistent with local land use plans and zoning ordinances IF after notice and hearing it determined it is in the public interest.  Alternatively, Siting Board decisions may be appealed through the Florida Appeals Court in the manner specified by the Final Order.
 

          E.      Public Notice by the Applicant 403.5115

Public notices are made by the applicant for all applications. The many different types of notices are outlined in the statute. The 2008 Legislative changes created some new obligations for the utilities regarding the application power plants and transmission line corridors. Notice of a certification hearing (discussed below in part K) must be published 65 days prior to the hearing. If alternate corridors have been accepted for consideration, the notice of certification has to include a map of all the proposed corridors.

Another major change from the 2008 Legislation is the requirement provided in 403.5115 (6). This requires the applicant to by a good faith effort, provide direct written notice of the filing of an application or certification no later than 45 days after the filing of the application to all landowners whose property and residences are located within the following distances of the proposed project:

  • 3 miles of the main site boundaries of the proposed electrical power plant

  • 0.25 miles of a proposed transmission line corridor.

  • 0.25 miles of all other linear associated facilities extending away from the main site boundary except for transmission line corridors.

No later than 60 days after the filing of the application, the applicant must provide the Department of Environmental Protection’s Siting Coordination Office with a list of landowners and residents who have been notified.

         Additionally, any proponent of an alternate corridor that includes a transmission line must provide direct written notice of the filing of an alternate corridor for certification no later than 30 days after the filing to all local landowners and residents whose property is located within 0.25 miles of the proposed boundaries of the corridor. Then, no later than 45 days after the filing of an alternate corridor for certification, the proponent of the corridor must provide the Department of Environmental Protection’s Siting Coordination Office with a list of those notified.

 For all other public notice requirements please review the full text of F.S. 403.5115

    FInformational Public Meetings 403.50663

         In order to facilitate the public’s understanding of the technical details about the project, as well as about the process, the Local Government within whose jurisdiction the power plant is proposed to be sited is encouraged in the Power Plant Siting Act to host an “Information Public Meeting”. The meeting’s purpose is also for the Local Government to obtain input from the public, and formulate a recommendation regarding the project. Essentially, the meeting functions like a community outreach open house. No votes or positions are required to be taken, and questions are encouraged.  If the Local Government does not choose to hold such a meeting, the Act encourages the Regional Planning Council to do so.  However, there is no penalty for not conducting one, nor requirement to do so.

         The Act recommends a timeframe for the conduct of this meeting (no later than 70 days after the filing of the application) such that the information obtained will be available prior to the deadline for the submittal of Preliminary Statements of Issues (see further below). The DEP and the applicant must attend these meetings, with the intended purpose of presenting the technical details and process description. Because of the need for the DEP/SCO and Applicant staff to attend, the Local Government/ Regional Planning Council (LG/RPC) must give them not less than five days notice of when and where it would like to host the meeting. The LG/RPC must also notify all the other parties to the proceeding. Because there may be several such meetings held if more than one LG/RPC is affected by the project, which may be the case if associated facilities are involved, scheduling may be an issue, so early notification is essential.

            If a local government or regional planning council chooses to hold an informational meeting, they must publish notice of the meeting within a newspaper of general circulation within the are in which the proposed power plant will be located no later than 7 days prior to the meeting.

        G.  Preliminary Statements of Issues 403.507(1)

         Each affected agency is required to submit this Statement to the DEP/SCO, the Applicant, and parties to the proceedings. The deadline for this submittal is no later than 40 days after the application has been determined complete.  This Statement is on the order of a "fatal flaw" analysis, or to highlight various problems with the project as proposed which have been noted early in the review.  A more detailed assessment will occur in the required agency reports (see further below).  Some agencies elect to provide this information along with their completeness comments.  If they do so, the Preliminary Statements need to be designated as such to separate them from completeness issues, as there can be major effects on the review schedule associated with completeness matters. 

        H.  Agency Reports 403.507(2)

         The Agency Reports, along with the internal reports from the DEP Districts and Bureaus, are the equivalent of Notice of Intended Agency Action on a Permit or Other Authorization.  Reports, other than the report required of the Public Service Commission, must be submitted to the DEP/SCO and the applicant no later than 100 days after the application has been determined complete. The Reports (other than the PSC’s) need to include:

  • an assessment of jurisdictional issues;

  • a recommendation whether the agency would approve or disapprove the proposal if the project were being judged solely on their own jurisdictional authority; if denial is recommended the reports should state why, and what might be done to correct the matter, e.g., redesign or relocation for all or any of the project features.

  •  the Conditions of Certification (permit provisos or other restrictions) recommended if the project is certified, whether or not the agency recommends certification.  Each proposed condition must identify the regulatory/authority basis for the condition, i.e., the specific statute, rule or ordinance governing the matter.

  • an assessment of any requested variances, exemptions, exceptions or other relief and a recommendation whether these should be granted.  The actual granting authority will be the Siting Board (or Secretary of DEP if the application is not disputed).

  • an assessment of any variances, exemptions, exceptions or other relief, and variances that would be required in order to approve certification but which were not requested in the application, along with a recommendation whether these should be granted.

  • an assessment of issues related to the use, connection to, or crossing of an agency-owned or controlled land. The Siting Board has the authority to direct any agency, within 30 days after certification, to execute any necessary license or easement to allow such usage.

  • a summary of the types of comments received from the public, along with information on how those comments were addressed, e.g., additional focus was given to an issue, the matter of concern was addressed in conditions relating to xxx, certain comments were not a matter under that agency’s jurisdiction and were referred to the appropriate agency.

*             If a report does not contain the information on proposed conditions or variances on the grounds that the agency does not recommend certification, the agency is considered to be waiving their rights to have any restrictions imposed, as the Siting Board may decide that it is in the overall public interest to certify the project, regardless of a negative recommendation.

         The Public Service Commission’s Report is of a different nature than the other agencies’ reports.  Essentially, all it is required to contain is a copy of the PSC’s Determination of Need, although the PSC may elect to provide other information.  This Report is due no later than 150 days after the filing of the application, and prior to the issuance of the DEP Project Analysis on the application (see below). If the report/Determination is negative, the remainder of the process essentially becomes moot, and stops.

         I.     Project Analysis 403.507(5)

         The DEP/SCO takes the reports and recommendations of the affected agencies, PSC, and DEP-internal District/Bureaus, and prepares a Project Analysis.  The Analysis must be filed (submitted) with the Administrative Law Judge and all parties no later 130 days after the application has been determined complete. By this time in the process, the outcome from a Siting Board hearing on Land Use, if one was necessary, should be available.  Also, the Notice of Intended Agency Action on federally delegated or approved permits (FDAP) should be available.  While these permits are not a direct part of the PPSA process, the matters at issue have a strong bearing on whether a project should be recommended for approval.  If the proposed agency action on a FDAP is denial, a recommendation of certification approval would be problematic.

         The Project Analysis must attempt to interweave all the varying viewpoints and come up with an overall picture of the issues.  It is the State equivalent of an Environmental Impact Statement. The Project Analysis is required to include the following items:

  • A statement indicating whether the proposed electrical power plant (and proposed ultimate site capacity) will be in compliance and consistent with:

(a)  the nonprocedural requirements of the affected agencies, as based upon the information provided by those agencies;

(b)  matters within DEP's standard jurisdiction (e.g., water quality, air quality, proprietary impacts on state-owned lands, State Park protections, etc.);

  • Copies of the Agency Reports, and any special studies conducted regarding the project;

  • The comments received by the department from any other agency or person (i.e., the public);

  • DEP’s recommendation regarding to the disposition of the application, of variances, exemptions, exceptions, or other relief identified by any party;

  • All proposed conditions of certification which the department believes should be imposed [duplicative conditions will be combined, when possible];

  • The recommendation of the department regarding the issuance of any license required pursuant to a federally delegated or approved permit program.

  • An overall recommendation whether the project must be approved, or denied.  If denial is recommended, the reasons why should be provided and corrective measures suggested.

          J.  Notice of the Certification Hearing 403.508(2)(b) and subsequently 403.5115(e)

         Notice of the hearing must be published in newspapers no later than 65 days before the hearing, and in the Florida Administrative Weekly no later than 45 days before the hearing.  Time-wise, the notice appears in-between the issuance of the agency reports and the issuance of the Project Analysis.  This is to assure ample opportunity for the public and substantially interested persons to review the Reports and Analysis and determine whether they wish to attempt to become formal interveners in the process. See earlier section B. on “Public Involvement and Parties to the Proceeding”, regarding this.

         As with the notice of application filing, the newspaper notice must be at least 1/2 page in size.  The newspaper notice will contain a map of the proposed project, including any associated facilities.  The notice will indicate the date of the hearing and location, along with the fact that the hearing may be cancelled if matters in dispute are resolved beforehand (see further below). If one or more alternate corridors have been accepted for consideration the notice of the certification hearing will include a map of all corridors proposed for certification.

       K.  Certification Hearing, Cancellation of the Certification Hearing

         A "Certification Hearing", which is conducted by an Administrative Law Judge, must be held if there are matters in dispute about the proposed project.  If there is not a dispute, the hearing may be cancelled (see further below for description of how this works).

(1)    Hearing Held 403.508 (2) and (3)

                 The hearing must be conducted “in a location in proximity to the proposed site”, although since many power plants are located in remote areas, the location of the hearing can be dictated by location and availability of a suitable meeting space near the power plant.  The hearings may last from a day to several weeks.

                 The hearing technically must commence no later than 265 days after the filing of the application is filed, although may be rescheduled if other scheduled items are postponed, such as if the application is not complete, or the parties are attempting to resolve disputes without the need for a hearing.  Federal permit program disputes may be combined, where possible, with this hearing, and so their time schedules may affect the commencement date.

                 Testimony and evidence will be presented at the hearing, and agency staff may be called upon to be witnesses.  Prior to the hearing, interrogatories may need to be answered, and depositions may be taken.  Each agency’s attorney should provide staff with guidance on these matters.   At the discretion of the Administrative Law Judge, the public may speak or submit written comments at this hearing, and oftentimes a special time is set aside for this purpose, typically in the evening.  Typically, the Administrative Law Judge will swear in commenters, and the parties have the right to cross-examine this “communication”, or to present evidence to the contrary.

              (2)  Hearing Cancelled 403.508 (6)

                 In a number of past cases, it became evident that, so long as the applicant agreed to all the proposed conditions of certification and other applicable use-of-properties restrictions, there was no need for a hearing.  Public testimony/comments were of a supportive nature, since these facilities can provide tax benefits to a community, along with jobs.  Because of this, and the expense of conducting an un-needed hearing, the 2006 Legislature amended the PPSA, allowing for the cancellation of the hearing before the Administrative Law Judge, as well as the one before the Siting Board.

                 In a case where it appears that no hearing is necessary, a stipulation (legal agreement) is initiated asserting that there are no disputed issues of fact or law to be raised at the certification hearing.  In order for the hearing to be cancelled, all parties to the proceeding must agree and sign the stipulation.  DEP or the applicant will then submit this stipulation to the ALJ with a request that the ALJ “relinquish jurisdiction” – release authority over the case -- which then drops the case from one considered to be under litigation.  The ALJ has five days to issue an order approving or denying the request.

                 The approval of cancellation must be accomplished in enough time for a large newspaper notice and a Florida Administrative Weekly notice to be published regarding the hearing cancellation at least three days prior to the date originally scheduled for the hearing.  It is hoped that everyone interested in the case will be apprised of the notice, and not travel to the previously announced hearing location.  However, some of the utilities have had staff present at the location to verbally advise such persons, in case this happens.

                 Once the ALJ has cancelled the hearing, the DEP prepares the Recommended Order that forms the basis for a Final Order of Certification signed by the Secretary (agency head) of DEP.  See further below for details of Recommended Orders and Final Orders.  To assist DEP in preparing the Recommended Order, the statute allows parties to submit proposed Orders to DEP for consideration. The Final Order must be issued by the Secretary within 40 days of the cancellation of the Certification Hearing.

         L.  ALJ Recommended Order 403.509

         If a Certification Hearing before the ALJ has been conducted, then within 45 days after receipt of the transcript of the Certification hearing, the Administrative Law Judge must issue a Recommended Order (RO).  This RO (and also the one prepared if the DEP Secretary will sign the Final Order) must contain finding of facts and conclusions of law about the matters raised at the hearing or in the application, along with the proposed Conditions of Certification if approval of Certification is recommended.  The eventual Final Orders, whether by the Secretary or the Siting Board, must address the criteria set out in s. 403.509(3), F.S. (discussed further below), and thus are discussed in the Recommended Order to set the basis for the recommendations.  The ALJ’s Recommended Order is submitted to the DEP for transmittal to the Siting Board.

         The agencies may file Exceptions to the ALJ’s Recommended Order with DEP if they feel something has been overlooked or incorrectly interpreted.  Agency staff may be asked to assist in reviewing the Order and preparing the Exceptions.

         The Recommended Order, Exceptions, and other pertinent data are then formulated into a Proposed Final Order that includes suggested action on the Exceptions.  An Agenda Package containing these items is sent to the Siting Board (Governor and Cabinet).  This work is done by the DEP Office of General Counsel and the DEP Cabinet Affairs Office.

         M.  Siting Board Hearing, Criteria for Certification

         The Siting Board must hold a hearing and act upon the application within 60 days of issuance of the ALJ's Recommended Order.   Prior to the full Cabinet hearing (usually the week preceding it), the Aides of the Governor and the Cabinet members conduct a meeting to discuss items on the upcoming agenda. 

         The Siting Board hearing normally is a subset of a standard Governor & Cabinet meeting and is normally held in the Capitol.  DEP presents the item, and responds to questions. The Applicant may answer questions as well.  If the Board chooses to do so, they may allow the public to speak.  In making its determination, the Board is limited to considering those matters raised in the certification hearing before the administrative law judge or raised in the Recommended Order. The hearing is not a forum to present new evidence or testimony.  Also, once the Board members have received the Recommended Order, it is forbidden for the parties or affected public to attempt to communicate directly with the Board members about the case outside of this proceeding, although the parties may communicate with the Aides.

         The criteria for the Siting Board and the DEP Secretary to use in determining whether an application should be approved in whole, approved with modifications or conditions, or denied [see s. 403.509(3), F.S.] must include consideration of whether, and the extent to which, the location of the electrical power plant and directly associated facilities and their construction and operation will:

                (a) Provide reasonable assurance that operational safeguards* are technically sufficient for the public welfare and protection. [*e.g., will the facility have fire control systems if a building were to catch on fire, or does the facility have adequate arrangements made with local fire safety providers.]

                (b) Comply with applicable nonprocedural requirements** of agencies.” [**Non-procedural requirements are regulatory standards or other terms prescribed and adopted for an agency authorization.  Examples include an air emissions limitation, a water quality limitation, and a height restriction for smokestacks in relation to an airport landing zone.]

                (c) Be consistent*** with applicable local government comprehensive plans and land development regulations. [***The term “consistent” is used, because not all plans/regulations have terminology specifically addressing power plants, but might have terminology for industrial uses, of which the plants might be considered a subset.]

                (d) Meet the electrical energy needs of the state in an orderly and timely fashion. [This criteria is determined by the findings of the Public Service Commission’s Determination of Need.]

                (e)  Effect a reasonable balance between the need for the facility as established pursuant to s. 403.519 [PSC’s Need Determination] and the impacts upon air and water quality, fish and wildlife, water resources, and other natural resources of the state resulting from the construction and operation of the facility.

         If the application is denied, an explanation must be given as to what could be done to make the project approvable.  If approved, the Order will be accompanied by Conditions of Certification

           Any transmission line corridor certified by the board must also satisfy the criteria above. When more than one transmission line corridor is proper for certification, the board, or the secretary where applicable, will certify the transmission line corridor that has the “least adverse impact regarding the criteria” set out above, including costs.

           If the board or the secretary, where applicable, find that an alternate corridor rejected pursuant to 403.5271 has the least adverse impacts based on the above criteria, they will deny the certification or allow the applicant to submit an amended application to include the alternate corridor.

           If the board or the secretary, where applicable, find that 2 or more of the corridors comply with the above criteria, and they are substantially equal in terms of adverse impacts, including costs, the board or secretary will certify the corridor preferred by the applicant.

         N.  Final Order Effective Date

         Once the Final Order is signed, it must be sent to the Clerk of the Siting Board for official entry.  The Clerk of the Department has been designated the Clerk for PPSA proceedings.  The certification will not become effective until "clerked-in".  Typically, this occurs several days after the Cabinet Hearing.


 

 III.  Post-certification Activities

         A.  Federally Delegated or Approved Permits (FDAPs)

         Final actions on FDAPS in relation to certification vary per type of permit, as follows:

  • Underground Injection Control (UIC) - The department's action may differ from the actions taken by the Siting Board if the federally approved permit program requires such a different action to be taken by the department.

        The department's action may differ from the actions taken by the Siting Board if the federally approved permit program requires such a different action to be taken by the department.

         The statute states that the review, processing, and issuance of the above FDAPS (Title V Air Operation permits are specifically not included) be closely coordinated with the certification process.  However, in the event of a conflict between the certification process and federally required procedures, the applicable federal requirements control.

         Regarding Title V Air Operation permits, these are not interwoven with the certification process, because the certification process is, for the most part, a construction permit.  It may take two to three years for the plant to become operational, and many intricate engineering details may change. The Air Operation permits will address any these changes, and eventually all the restrictions are interwoven into the Conditions of Certification by a Modification to incorporate the Title-V permit by reference.

          B.  Agency Lands and Works 403.509(5)

         The Siting Board is given under the PPSA the authority to decide issues relating to the use, the connection to, or the crossing of the properties and works of any agency which is a party to the certification hearing for matters pertaining to the power plant and directly associated facilities. The Siting Board can direct any such agency to execute, within 30 days after the entry of certification, the necessary license or easement for such use, connection, or crossing, subject only to the conditions set forth in such certification.

  

 

 

NEW

Last updated: August 13, 2008

  2600 Blair Stone Rd M.S. 48   Tallahassee, Florida 32399   850-245-8002 (phone) /  850-245-8003 (fax)
 
DEP Home | About DEP  | Contact Us | Search |  Site Map