Owners or operators of facilities regulated by the
Solid Waste Financial Assurance office shall annually adjust their
facility closure cost estimates for inflation and submit updated
information to the Department. Outlined below are Rule
62-701.630(4), Florida Administrative Code (F.A.C.), requirements
for submission of closure cost estimates.
- Form 62-701.900(28) is used to prepare and submit closure cost estimates. Contact your permitting office for assistance
with the form.
- Annual cost estimate adjustments may be made either by
recalculating the maximum cost of closure or by using the
current year inflation factor.
- For owners or operators using an escrow account to
demonstrate financial assurance, cost estimates must be
submitted between July 1 and September 1 of each year.
- For owners or operators using an alternate financial
mechanism to demonstrate financial assurance, cost estimates
must be submitted between January 1 and March 1 of each year.
- Please submit Form 62-701.900(28) to the appropriate
permitting office with a copy to:
Solid Waste Financial Coordinator
Department of Environmental Protection
2600 Blair Stone Road MS 4565
Tallahassee, Florida 32399-2400
(850) 245-8732 FAX (850) 245-8811
Calculation of the Inflation Factor
- The annual inflation factor is derived from the most recent
Implicit Price Deflator for Gross National Product published by
the U.S. Department of Commerce in its Survey of Current
Business, pursuant to Rule 62-701.630(4)(b)(2), F.A.C.
- To calculate the current inflation factor, divide the latest
published annual Deflator by the Deflator for the previous year.
- Implicit Price Deflator data is published by the U.S.
Department of Commerce, Bureau of Economic Analysis on their
website,
http://www.bea.gov .
| 1.030 |
for estimates due between January 1 and March 1, 2008 |
| 1.025 |
for estimates due between July 1 and September 1, 2008 |
Recent Inflation Factors:
2000 Cost Estimate x 1.020 = 2001 Cost Estimate
2001 Cost Estimate x 1.020 = 2002 Cost Estimate
2002 Cost Estimate x 1.010 = 2003 Cost Estimate
2003 Cost Estimate x 1.015 = 2004 Cost Estimate
2004 Cost Estimate x 1.020 = 2005 Cost Estimate
2005 Cost Estimate x 1.030 = 2006 Cost Estimate
2006 Cost Estimate x 1.030 = 2007 Cost Estimate
2007 Cost Estimate x 1.025 = 2008 Cost Estimate
|